SRINAGAR,
AUGUST 5: Chief Secretary, B B Vyas today
reviewed the status of road infrastructure network in the state assigned to
Project Beacon, Sampark and Himank of the Border Roads Organization (BRO).
While
Project Beacon is assigned the road development work in all three regions of
J&K, Project Sampark is mostly tasked with the improvement and development
of roads in Jammu-Rajouri-Poonch sector and Project Himank for Ladakh region.
Commissioner/Secretary,
PW(R&B), Commissioner Secretary, Revenue, Chief Engineer’s of Project
Beacon, Project Sampark, Chief Engineer, R&B, Kashmir, Chief Engineer,
PMGSY, Kashmir and other senior officers participated in the meeting.
Divisional Commissioner, Jammu, Divisional Commissioner, Kashmir and DCs of
Baramulla, Kupwara, Bandipora, Ganderbal, Leh, Doda, Poonch, Rajouri, Kishtwar,
Samba, Kathua participated in the meeting via video conferencing.
While
highlighting the crucial role being played by BRO in improving road
connectivity across the three regions of the state, Chief Secretary urged BRO
to expedite work on all critical roads. He further impressed upon the concerned
Administrative Secretaries, Divisional Commissioner Jammu, Divisional Commissioner,
Kashmir and DCs to coordinate with BRO and draw up timelines for early
resolution of issues related to land acquisition, forest clearance, shifting of
utilities and disbursement of compensation.
“Timely
completion of road projects is vital for growth and development of the state”
Chief Secretary observed.
Chief
Secretary reviewed the status of Project Beacon roads including
Bandipora-Gurez, Chowkibal-Tanghdar-Chamkot, Kupwara-Kalaroos-Machil,
Srinagar-Sonmarg-Gumri, Srinagar-Baramulla-Uri, Basohli-Bani-Bhaderwah Mahi-
Dipling, Sakti-Agyam, Nimoo-Padum and Loma-Demchok road etc.
He also
reviewed the status of Project Sampark and Project Himank roads including
Reasi-Arnas-Mahore, Rajouri-Thanamandi-Surankote, Bani-Basholi, Kalai Bridge
approach, Gali-Aganpathri, Chadwal-Sanjimore-Paharpur-Simble, Khet CRP Dhok,
Reasi-Pouni-Siar-Rajouri, Bhawani-Dharal, Rajpura-Madwal-Phulpur,
Agrachak-Rspura-Dablihar-Rathana-Arnia-Khour, Shahstar-KG Top,
Domel-Jindrah-Kharta and Rajouri- Kalakote road etc.
BRO was also
requested to expedite work on various roads in Keran and Tangdhar sector and
prioritizing finalising of DPR for Sadna Tunnel.
In order to expedite resolution of
issues and completion of all BRO projects, Chief Secretary impressed upon DCs
to hold review meetings in every 3rd week of the month.
The progress
of BRO projects will again be reviewed in September, 2017 by the Chief
Secretary.