Asks for early
survey of Khandyal-Vijgali road
JAMMU, APRIL 12: Deputy Speaker, Jammu and Kashmir Legislative
Assembly, Nazir Ahmad Gurezi Thursday instructed the Forest, BECON
and Public Works Departments to conduct joint inspection for fixing up the
aliment of Khandyal to Vijgali road in Tehsil Gurez.
In this regard,
he asked them to submit the report to the concerned quarters within a month to
seek necessary sanction for early start of the construction work of the
project.
The Deputy
Speaker was chairing a meeting of the officers of Forest, Public Works
Department and BECON authorities convened to discuss and sort out various
issues related to road connectivity in Gurez.
The Deputy
Speaker sought status of forest clearance of proposed raod projects,
construction of tunnels and grant of permission for installation of crushers.
Taking stock of
pace of progress on Bandipora Gurez Chakwali road, the Deputy Speaker asked the
Forest Department to complete demarcation of one hector forest land acquired by
the BECON for the purpose within a week’s time. He also asked the BECON
authorities to speed up the pace of work on the project and complete it in a
stipulated time frame.
It was decided in
the meeting that the BECON will hand over the main road from Wonpora Bridge to
Markote Bridge crossing to PWD and likewise PWD will hand over the newly
constructed road from Wonpora bridge to Markote bridge up to Helipad to BECON
for development and maintenance.
About the
development of road from Razdan Pass to Gurez, the BECON authorities informed
the meeting that the necessary permission may be granted to install crusher
machine. The Deputy Speaker asked the district administration Bandipora to
issue necessary permission under rules at an earliest so that the construction
work on the road does not suffer.
The Deputy
Speaker further directed the concerned to machdamize at least 15 km road
length in Tehsil Gurez including Tulail upto Neeru during the current fiscal.
He also asked them to construct bridge at Z-Kushi.
Taking stock of
the status of proposed construction of Bandipora-Gurez tunnel project, the
BECON authorities informed the meeting that the centre government has given its
nod for the project and necessary formalities are under process.
It was given out
in the meeting that improvement and upgradation of Athwatu to Bunkote -
Sonarwani road project has been sanctioned under CRF at an estimated cost of Rs
15 crore.
Meanwhile, the
Deputy Speaker asked the Forest, BECON and R& B Department to work with
utmost dedication, unison and ensure timely completion of all road projects. He
also asked concerned to closely pursue the proposed road projects under Asian
Development Bank and CRF forwarded to the centre government.
The meeting was attended by the Development Commissioner Works, Satish
Razdan, Chief Conservator of Forest, Abdul Gani, Additional Secretary Forest,
Ecology and Environment, Mohammad Ashraf Hakak, Additional Secretary Forest,
Special Secretary (Technical) Forest Department, K Raniesh Kumar, Cdr 32 BRTF,
Col Amit Chander, OC 56 RCC BECON, Maj APS Khana, SE R&B Bandipora, Mushtaq
Ahmad, Divisional Forest Officer, Bandipora and other concerned officers of
Forest, PWD and BECON.