JAMMU, MAY 15: To carry out work of branch cutting
and preventive maintenance, the shutdown of 33 KV NITs Chatha Tap Line is being
observed.
During the shutdown, the power supply to Hakkal,
Raipur, Satwari, SKAUST, Chatha and its adjoining areas will remain affected onMay
16 from 9 am to 2 pm.
Meanwhile, for shifting of electrical utilities of
11 KV SC-5 feeder coming in the alignment of construction of deep drain
nallahs, the shutdown of 33 KV Channi-Sainik Colony line is being observed.
During the shutdown, the power supply to Channi,
Sainik Colony and its adjoining areas shall remain affected from May 16 to May
28 from 9 am to 10 am.
Similarly, to execute work of branch cutting for
smooth running of power supply, the shutdown of 11 KV JDA-2, JDA-4, JDA-7,
TRN-1, TRN-2, TRN-3 and TRN-4 feeders is being allowed.
During the shutdown, the power supply to Bahu
Plaza, Shiv Market its adjoining areas and Vodafone Installation shall remain
affected on May 16 from 7 am to 11 am.
Similarly, the power supply to Sec-1, 2, 3 and
extensions of Trikuta Nagar, Marbel Market, Adarsh Enclave and its adjoining
areas shall remain affected on May 16 from 8 am to 11 am.
Likewise, the power supply to Bahu Plaza,
Divisional Commissioner Office Complex, Mangal Market and its adjoining areas
shall remain affected on May 20 from 9 am to 12 noon.
However, to carry out various development works by
M/s IRCON International Ltd under scheme R-APDRP Jammu, the power supply to
Sainik Colony, Chowdhi, Birpur, Ratnuchak, MES, Kaluchak and its adjoining
shall remain affected on May 16 and 18 from 9 am to 1 pm.
Similarly, the power supply to Shakti Nagar,
Rajpura, Canal, Krishan Nagar, Dogra Mohalla, Science College, Old University
and its adjoining areas shall remain affected on May 16 from 9 am to 1 pm.
Likewise, the power supply to Sainik Colony and its
adjoining areas shall remain affected on May 16 and 18 from 9 am
to 1 pm.