SRINAGAR, JULY 13: The Planning and Development
Department has issued guidelines for implementation of Constituency Development
Scheme (CDS) during the Suspended Animation of the State Assembly.
According to a
circular issued by the Department, all District Development Commissioners
(DDCs) have been instructed for execution of all ongoing works under
Constituency Development Scheme (CDS) and the same shall be completed as per
the existing timelines.
Similarly,
works for which either administrative approval has been accorded or detailed
estimates have been prepared but not physically commenced shall be executed
expeditiously after accord of administrative approval and completion of all
prescribed codal formalities subject to the availability of funds in the
account of Legislators (available unspent balance to be calculated after accounting
for both completed and ongoing works).
Meanwhile,
works which have been identified prior to the pronouncement of State Assembly
being placed under Suspended Animation, but wherein estimates for the work have
not been prepared or authorized, shall also be considered for grant of approval
by the District Development Commissioners subject to the fulfillment of CDS
guidelines and availability of balance funds in the account of Legislator.
It has been
further impressed upon all District Development Commissioners to devise a
foolproof mechanism to ensure that no back date authorizations are received.
Besides, DDCs
shall within one week of
authorizations to all pending works, furnish a work wise list to PD&MD. Any
violation noticed as a result of this exercise shall not only lead to
cancellation of works but shall also invite an appropriate administrative
action; ii. Personally supervise and monitor the pace and quality of execution
of work at regular intervals to ensure their completion without any cost or time
over run for larger public good.
The DDCs, for this purpose, shall intensify their
field visit and public outreach programmes. DDC shall also report the fiscal
picture (reckoning expenditure and projected expenditure in pursuance to this
circular) to PD&MD by or before August 31st, 2018.
3. The PD&MD would be free to get any random/ other checks or
verification(s) conducted to ensure/ ascertain that the works authorized are in
general public interest and in conformity with CDS guidelines.