Calls for regular monitoring; Seeks fortnightly progress report
SRINAGAR, SEPTEMBER 06: Expressing
dissatisfaction over the sluggish pace of work by three Central PSUs on
augmentation of power transmission and distribution infrastructure in J&K,
Union Minister of State for Power (Independent Charge), R K Singh today said
there is absolutely no scope for lackadaisical approach and the works shall
have to be completed within the set time-frame.
Speaking at a meeting chaired by Governor Satya Pal Malik at SKICC here
today to review the progress of power sector schemes in J&K, the Minister
asked the State Chief Secretary, B V R Subrahmanyam to submit fortnightly
update directly to his office on the implementation of Rs 2500 crore works
allotted to Power Grid Corporation of India Limited (PGCIL), Rural
Electrification Corporation Power Distribution Company Limited (RECPDCL) and
REC Transmission Project Company Ltd (RECTPCL)under Prime Minister's
Development Programme (PMDP), Integrated Power Development Scheme (IPDS),
DDUGJY and R-APDRP.
Advisor to Governor, B B Vyas (Incharge Power Department) informed the
Minister that he will be also taking regular review meetings to monitor the
progress of these works.
The Minister also asked these PSUs to establish their camp offices in
Srinagar and keep senior officers stationed in the state’s summer capital for
regularly monitoring the progress of works in Kashmir and Ladakh.
Responding to the plea of the State Government for bringing down the
Project Implementing Agency charges fixed at 8% for transmission, 8.5% for
distribution works by these PSUs, the Minister said the issue would be looked
into favorably and the PSUs would be asked to levy uniform rate of 5% as PIA
charges.
Earlier, in his presentation, Commissioner Secretary, Power Development
Department (PDD), Hirdesh Kumar informed the meeting that there has been only
5% physical progress on the works allotted to these PSUs in February this year.
He said RECPDCL has been engaged for execution of distribution works for
Jammu, Kashmir and Ladakh areas for Design, Engineering, Procurement supply,
erection, testing and commissioning of all the material and services works to
be taken-up for execution of distribution works under IPDS, PMDP and R-APDRP in
5 circles of J&K at an estimated cost of Rs931.33 crore.
Power Grid Corporation of India Limited (PGCIL) has been allotted
execution of distribution works for Jammu, Kashmir and Ladakh areas for Design
Engineering, Procurement, supply erection testing and commissioning of all the
material and services works to be taken-up for execution of Sub- transmission
and distribution works of 8 Districts under RGGVY-II, DDUGJY and PMDP (Rural)
at an estimated cost of Rs 507.73 crore and for execution of transmission works
in Jammu, Kashmir and Ladakh areas at an estimated cost of Rs 426.13 crore
under PMDP. Similarly, RECTPCL has been allotted execution of transmission
works for Jammu, Kashmir and Ladakh areas for Rs 495.54 crore under PMDP.
The MoU was signed with all these PSUs for execution of these works in
February 2018.