SRINAGAR, SEPTEMBER, 7: Chief
Secretary, B B Vyas Thursday chaired the 3rd Apex Committee meeting here to review the progress of
Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project.
Chief Administrative Officer (CAO), USBRL Project, Commissioner/Secretary,
Forests, Ecology & Environment, Divisional Commissioner, Kashmir and other
senior officers of the State Government and Railway authorities were present in
the meeting. Divisional Commissioner, Jammu, Deputy Commissioners, Reasi and
Ramban participated via video conferencing.
Chief Secretary received brief from Divisional Commissioner, Jammu,
Deputy Commissioner, Reasi and Deputy Commissioner, Ramban regarding the latest
status of land acquisition in the Katra-Banihal Rail Line section and 132 KV
Transmission Line section from Katra to Reasi and Ramban to Sangaldan for the
Railway’s Integrated Sub-Station.
Railways Authorities were requested to complete the work on the railway
crossing at Bijbehara at the earliest, so that traffic on this National Highway
stretch is thrown open without any encumbrance.
Chief Secretary also reviewed the progress of 4 lane Srinagar-Jammu
National Highway projects and 4 lane Srinagar/Jammu ring road project. He
received brief regarding the status of these projects from both Divisional
Commissioners and concerned DCs.
Chief Secretary asked DCs to expedite the disposal of pending land
acquisition cases in all the three prestigious projects.
Commissioner
Secretary R&B, representatives of NHAI and concessionaires and other senior
officers were also present in the meeting.