JAMMU MARCH 02: To carry out maintenance work on OPGW on existing
132 KV Jhajjarkotli-Janipur line, the shutdown of 132 KV Jhajjarkotli-Janipur
line from 132/33 KV Grid Station, Janipur is being observed.
During the shutdown, the power supply to Jhajjarkotli,
Jindrah Flata and adjoining areas shall remain affected on March
4 from 9 am to 2 pm.
Meanwhile, to execute work for preventive
maintenance, branch cutting and thickening of 33 KV G-7 line, the shutdown of
33 KV G-2, G-3 G-7 lines is being observed.
During the shutdown, the power supply to Gandhi
Nagar, Bahu Plaza, Part of Trikuta Nagar, Jammu University, Divisional
Commissioner Office, Bikram Chowk and its adjoining areas shall remain affected
on March 5 from 7 am to 10 am.
Similarly, the power supply to Nanak Nagar, Shastri
Nagar, Part of Gandhi Nagar and its adjoining areas shall remain affected onMarch
5 from 7 am to 10 am.
Likewise, the power supply to Channi Himmat, Malik
Market, PHQ Channi Himmat, Sainik Colony, Chowadi, Transport Nagar, Fruit
Mandi, Narwal Bathindi PHE installation and its adjoining areas shall remain
affected on March 4 from 9 am to 2 pm.
Meanwhile, to carry out the installation and
commissioning of isolators, the shutdown of 132/33 KV Kalakote-Rajouri
Transmission Line is being observed.
During the shutdown, the power supply to Kalakote,
Sunderbani, Nowshera and its adjoining areas shall remain affected on March
4 from 9 am to 4 pm.
Similarly, to carry out work for replacement of 33
KV isolators of 33 KV Bay under PSDF work, the shutdown of 33 KV feeder Kullian
emanating from 132/33 KV Miran Sahib Grid Station is
being observed.
During the shutdown, the power supply to Kullian
(R.S. Pura) and its adjoining areas will also remain affected on March
3 from 9 am to 4 pm.
However, for conducting de-stringing work of 132 KV
Transmission Line between Tower location 10 and 11 of 132 KV Canal-Miran Sahib
Transmission Line under Airport Expansion Project, the shutdown of 33 KV Feeder
Canal-Chatta emanating from 132/33 KV Canal Grid Station is being observed.
During the shutdown, the power supply to Sohanjana,
Mandal, Flian, Khandwak, Surya Chak, New Satwari, Air Force, Military Hospital,
New Basti, Narwal Pine, Airport, Military Cantt, Shastri Nagar, Digaina,
Satwari and its adjoining areas will remain affected on March
3 from 10 am to 2 pm.