JAMMU, JANUARY 23: In order to carry out stringing of conductor on newly erected poles of 33 KV Vijaypur line emanating from 132/33 KV Grid Station BB-1, the power supply to Vijaypur, Ramgarh and its adjoining areas shall remain affected on January 24 and 28 from 10 am to 04 pm.
Meanwhile, to carry out various development works by M/S. IRCON under R-APDRP Scheme, the power supply to Gandhi Nagar and its adjoining areas fed from 11 KV RC-1, RC-7 and JDA-1 feeders shall remain affected on January 24 and 27from 10 am to 02 pm.
Similarly, the power supply to Babliana and its adjoining areas fed from 11 KV BL-3 feeder shall remain affected onJanuary 25 from 10 am to 02 pm.
Likewise, the power supply to Channi Himmat and its adjoining areas fed from 11 KV CH-8 feeder shall remain affected onJanuary 24 from 10 am to 02 pm.
Meanwhile, the power supply to Channi Himmat and its adjoining areas fed from 11 KV CH-6 feeder shall remain affected on January 24 and 27 from 10 am to 02 pm.
Similarly, the power supply to Satwari, Shastri Nagar and its adjoining areas fed from 11 KV SA-9 and SN-1 feeders shall remain affected on January 24 from 10 am to 02 pm.
Likewise, the power supply to Nai Basti, Satwari and its adjoining areas fed from 11 KV SA-3 feeder shall remain affected on January 24 from 10 am to 02 pm.
Similarly, the power supply to Trikuta Nagar and its adjoining areas fed from 11 KV TRN-1, 2 and N-9 feeders shall remain affected on January 24 and 27 from 10 am to 02 pm.



SRINAGAR, NOVEMBER 10: According to Chief Engineer, EM&RE Wing, Kashmir, in order to carry out cutting down of Poplar trees, power supply from 33 KV lines of STD IInd, Srinagar shall be affected on November 11, 2017 from 11 am to 01 pm and 33 KV line from Amargarh Pattan line shall be affected on November 14, 2017 from 11 am to 02 pm.

Power supply to these areas fed from these lines shall remain affected on said dates and times.

          JAMMU NOVEMBER 10:In order to carry out various development works by M/s IRCON International Ltd under R-APDRP scheme, the power supply to Colonel Colony, Hazuri Bagh and adjoining areas fed from T-2 (Toph) feeder shall remain affected on November 13 and 15 from 9 am to 1 pm.
          Similarly, the power supply to Birpur Complex, Kaluchak, Kanhal, Seora, Bari Brahmana Industry, Greater Kailash and adjoining areas fed from BB-I Grid to Birpur Complex 33 KV Line and 11 KV Kaluchak Line shall remain affected on November 12 from 8 am to 2 pm.
          Likewise, the power supply to Gandhi Nagar and adjoining areas fed from 11 KV JDA-I feeder shall remain affected on November 13 and 15 from 9 am to 1 pm.

        
  JAMMU NOVEMBER 08: In order to carry out the erection of 66/11 KV, 1x6.3 MVA Transformer and dismantling of 66/11 KV, 1x10 MVA Transformer at 66/11 KV R/Stn Hatlimore, the shutdown of 66 KV Industry Feeder and 66/11 KV R/Station Hatlimorh-I is being observed.
          During the shutdown, the power supply to CTM, SICOP, SIDCO, MES-Janglote, Patel Nagar, Ram Nagar, Shiva Nagar, Kalibari, Hatlimorh, Taranagar, Govinsar, DC Office Complex, Shastri Nagar, Ward No. 06, Ward No. 07 and its adjoining areas shall remain affected on November 09 from 10 am to 4 pm.

          Meanwhile, to execute maintenance work at 33/11 KV Receiving Station Dairy Farm, the power supply to 33/11 Receiving Station Dairy Farm, Sataney, Pathi, Ramnagar, Chowki, Majouri and Basantgarh fed from Udhampur-Dairy Farm (Army Line) & Ramnagar shall remain affected on November 10 from 8 am to 2 pm.

          SRINAGAR, NOVEMBER 07:  In order to carry out replacement of 33KV isolator of 30 MVAR shunt capacitor, top tiers, droppers, jumpers etc and other maintenance work in the grid station, shutdown of 150 MVA/33KV Grid Station, Bemina will be carried on 11, November 2017 from 9AM to 5PM.

          The power supply to the area fed from the grid station shall remain affected on the said date and time.

JAMMU NOVEMBER 03: In order to carry out shifting of 33 KV BH-2 line coming into alignment of road for Parking of High Court, Jammu, the power supply to Muthi, BSF Paloura, Barnai, Lower Muthi, Upper Muthi, MES, Muthi PHE, Roop Nagar PHE, Barnai PHE, Upper Domana, Patoli, Paloura and adjoining areas shall remain affected on November 05 from 08 am to 05 pm.
Similarly, the power supply to Canal Road, Shakti Nagar, Talab Tillo, Udheywalla, Bohri, Jewel, Company Bagh, Camp Gole Gujral, Gho-Manasan, Marh, Gajansoo, Ashok Nagar, Chatha, Satwari, Satwari Cantt and part of Shastri Nagar fed from 132 KV Barn-Canal Double Circuit Line shall remain affected on November 05 from 08 am to 05 pm.
Meanwhile, to carry out various development works by M/S. IRCON under R-APDRP scheme, the power supply to Gandhi Nagar and adjoining areas fed from 11 KV JDA-1 feeder shall remain affected on November 07 and 09 from 08 am to 12 noon.
Similarly the power supply to Channi Himmat and adjoining areas fed from 11 KV CH-4 feeder shall remain affected onNovember 05 from 10 am to 12 noon.
Likewise, the power supply to Birpur Complex, Kanhal, Seora, Greater Kailash, Bari Brahamana Industrial Area, Kaluchak and adjoining area fed from BB-1 Grid to Birpur Complex 33 KV line and 11 KV Kaluchak feeder shall remain affected onNovember 05 from 08 am to 02 pm.
Meanwhile, to carry out work painting of ST poles, the shutdown of 11 KV Kanhal feeder emanating from 33/11 KV R/Stn Birpur Complex is being observed.

During the shutdown, the power supply to Upper Kanhal, Lower Kanhal, Palli, Kothi Morh, Bassi Kalan and Bassi Khurd shall remain affected on November 5 from 9 am to 5 pm.


JAMMU NOVEMBER 02: To carry out the work of construction of  400 KV D/C Samba-Amargarh Transmission Line (Package-I) regarding the shutdown of 11 KV Line for stringing work at LOC No. 61/0 & 62/0, the shutdown of 11 KV Rakh Muthi Feeder is being observed on November 03 and 04 from 10 am to 4 pm.

          JAMMU, NOVEMBER 01: To carry out the stringing work of 400 KV Double Circuit  Dulhasti-Kishenpur Transmission Line, the shutdown of 33 KV Thathri to Gandoh Line, Thathri to Chowdary Power Project Line and 11 KV Thathri to Khara Line is being observed.
During the shutdown, the power supply to Khara, Bunjwah, Jangalwar, Jakyas, Chillipingal, Gundoh, Bhatyas, Thathri, Changa and Saroor to which power supply at 11 KV level is supplied through 33/11 KV R/stations Thathri, Bhatyas, Gandoh and Changa shall remain affected on November 5 from 10 am to 3 pm.

Meanwhile, to carry out the work of laying of AB Cable to SMVD IME installation, the power supply to Panthal fed from 33 KV Jhajhar Kotli-Panthal Line shall remain affected on November 2 from 7 am to 1 pm.


          SRINAGAR, OCTOBER 31: According to Superintending Engineer EM&RE, Circle-I Srinagar, in order to execute urgent maintenance of 220/132kv grid station Pampore, the power supply from 132/33kv grid stations Rawalpora, Cheshmashahi, Pampore, Awantipora and Lassipora shall remain affected on November 1, 2017 for 2 to 3 hours.