JAMMU, JULY 15: In order to carry out
various development works by M/S. IRCON International Ltd under R-APDRP scheme,
the power supply to MES, Kalu Chak, Birpur, Data Talab, Madana and Ratnu Chak
fed from 33 KV Ratnu Chak Feeder shall remain affected on July 15, 17, 19, 21 and
25 from 07 am to 12 noon.
Similarly, the power supply to MES,
Kalu Chak, Birpur, Data Talab, Madana, Ratnu Chak and Industrial area of Bari
Brahamana fed from 33 KV Ratnu Chak and BB-2 feeders shall remain affected
on July 23 from 07 am to
12 noon.
Likewise, the power supply to
Industrial area, SIDCO Bari Brahmana fed from 11 KV BB-21 feeder shall remain
affected on July 17, 19 and 21 from 07 am to 09 am.
Meanwhile, the power supply to Muthi
and adjoining areas fed from 11 KV T-4 and MU-05 feeders shall remain affected
on July 16, 18 and 20 from 07
am to 11 am.
Similarly, the power supply to
Janipur Colony and adjoining areas fed from 11 KV J-3 feeder shall remain
affected onJuly 17, 19 and 21 from 07 am to 11 am.
Likewise, the power supply to
Babliana and adjoining areas fed from BL-2, BL-5 and BL-3 feeders shall remain
affected on July 16, 17, 18 and 19 from 07 am to 11 am.
Meanwhile, the power supply to
Sohajana, Mandal, Flian,Kandwal, Surya Chak, Ganeshpur and adjoining areas fed
from 33 KV Canal to Chatha Line shall remain affected on July
17 and 19from 07 am to 12 noon.
Similarly, the power supply to Channi
Himmat and adjoining areas fed from 11 KV CH-3 feeder shall remain affected
onJuly 17 and 19 from 07 am to 11 am.
Likewise, the power supply to Gandhi
Nagar and adjoining areas fed from 11 KV JDA-1 feeder shall remain affected
onJuly 18 and 20 from 07 am to 11 am.
Meanwhile, the power supply to Sainik
Colony and adjoining areas fed from 11 KV SC-2 and SC-1 feeder shall remain
affected on July 16, 17, 18, 19 and 21 from 06 am to 10 am.
Similarly, the power supply to Purani
Mandi, Parade, Link Road, Shalimar, Pacca Danga, Bus Stand, Raghumnath Bazaar,
Kanak Mandi, Partap Garh, PHE Parade, Telephone Exchange, Ranbir Market and
adjoining areas fed from 33 KV Company Bagh-Parade Tap Line and 33/11 KV
Transformer Bank-II at Receiving Station New Sectt shall remain affected onJuly 16 from 6.30 am to 8.30 am.