SRINAGAR, JULY 12: According to the Power Controller,
Kashmir Province, Srinagar, in order to carry our branch cutting and other
minor repairs, shutdown of 132/33KV Grid Stations Awantipora on July 14 and
Grid Station Lassipora, 132 KV ATL Ckt Ist & II on July 22, 2018 shall
be taken from 9 am to 6 pm. Shut down on Grid Station Wanpoh (33KV
side) on July 14, 2018 and Grid station Wanpoh on July 16 &
18, 2018 shall be taken on 9 am to 3 pm.
Also shut down on
33 KV lines of Pampore-Chadoora and Pampore-B.K. Pora shall be taken on July
14 and 16, 2018 and Rawalpora-Baghi-Mehtab onJuly 16, 2018 from 10 am to 4
pm.
Meanwhile, to
ensure uninterrupted power supply to yatra base camp at Magam and Baltal,
shutdown of Badampora Safapora line shall be taken onJuly 14, 2018, Badampora HCC
line on July 16, 2018, and Safapora Bandipora line on July 23, 2018,
from 9 am to 5 pm.
The power supply to the areas fed from these receiving/grid stations
shall remain affected on the said date and time.